Role
Prime Contractor
ZGC managed the public-agency contract, site coordination, subcontractors and closeout.
Public Infrastructure | Plano, Texas
ZGC served as prime contractor for retaining-wall masonry restoration, riprap installation, bridge-abutment erosion protection and associated sealing work at the North Texas Tollway Authority's Gleneagles facility in Plano.
Role
ZGC managed the public-agency contract, site coordination, subcontractors and closeout.
Final Contract
Final contract value including the approved change-order work.
Erosion Control
Approximately 20 tons of specified Type H riprap were installed at the bridge-abutment erosion area.
Closeout
Perfect punch, no defects, no warranty callbacks and no post-completion corrective work.
The Site Problem
The project addressed two different but related infrastructure conditions: deterioration in an existing stone retaining wall and erosion undercutting adjacent bridge-footing and abutment areas.
ZGC coordinated the masonry restoration and erosion-control scopes under one public-agency prime contract. The work had to be sequenced under controlled-access conditions during daytime operations.
The solution combined repair of the existing masonry rather than wholesale replacement with engineered rock placement to protect the bridge-abutment area from continued erosion.
Project Profile
Masonry Restoration
ZGC self-performed the mortar repointing and stone-repair portion of the work while coordinating the overall project and specialty subcontractors.
Existing wall and affected surfaces were cleaned to expose deteriorated areas and prepare the masonry for repair.
Deteriorated mortar was removed and replaced, joints were repointed and damaged stone conditions were repaired.
The repaired retaining wall and bridge/handrail areas received specified sealing work as part of the completed restoration package.
Bridge-Abutment Erosion Protection
ZGC coordinated installation of approximately 20 tons of Type H riprap at the bridge-abutment erosion area. The specification called for large, durable rock meeting defined gradation, density and durability requirements.
The placement strategy required the rock to be installed from the toe upward, distributed to minimize voids and interlocked so smaller material locked between the larger stone.
The work provided a durable erosion-control layer at the affected bridge-footing area while integrating with the existing site conditions. The project supports ZGC's broader Dallas-Fort Worth commercial general contracting and facility-repair past performance.
Riprap Specification Highlights
Project Delivery
ZGC served as the prime contractor and managed three subcontractor companies while directly performing the retaining-wall mortar repointing and stone-repair work.
The contract included one approved change order for additional retaining-wall repair, repointing and sealing work near the handrail area.
Following completion and inspection, NTTA confirmed the project was ready for invoicing. The project closed with no punch-list discrepancies, no defects and no warranty callbacks.
Final Schedule of Values
Related Capabilities
Masonry repair, repointing, exterior restoration and multi-trade existing-condition repairs throughout Dallas-Fort Worth.
Prime-contract construction, renovation and repair for federal, state and local agencies across Texas.
Subcontractor coordination, field management, quality control and closeout for complex commercial and institutional scopes.
Public and Commercial Facility Repair
ZGC manages targeted repair scopes where access, sequencing and restoration quality matter.